August 31, 2021 – In August, Phoenix Paper finished a 5M recommissioning project for our Pulp Dryer.

The addition of the Pulp Dryer will allow Phoenix Paper to more efficiently operate the back end of the mill, as well as add a secondary product of baled pulp.

The project was complex, upgrading former equipment and raising the roof of the building to accommodate the newer standard size of rail cars.

The project was completed on time, on budget, with zero injuries.